South Africa: Once-Abandoned Vleifontein Library Nearing Completion At Last

[ad_1]

Construction on the R16-million facility began in September 2022

After long delays, the multi-million-rand Vleifontein Library in Limpopo is finally nearing completion. Initially seen as a beacon of hope for the community, the project faced numerous setbacks but now promises to deliver much-needed educational resources. Nearby villages, such as Maila and surrounding areas, will also benefit.

Construction began in September 2022 but halted after just two months when Malerate Construction, which was awarded the R10.6-million tender, apparently abandoned the site.

In December 2022, Malerate officially withdrew, citing labour strikes, excessive SMME demands, adverse weather conditions, and rising interest rates.

Limpopo public works, in consultation with the Department of Sport, Arts and Culture, terminated Malerate’s contract on 20 December 2022.

The stoppage left the community frustrated and demanding accountability. Residents watched helplessly as the incomplete building, intended to be a cornerstone of education, stood idle.

In March 2023, the department revealed it had paid the contractor R743,000 for work completed.

Initially it was anticipated that a new contractor would be appointed in April 2023, with the library’s completion expected by May 2024.

But this timeline did not materialise. The delay has forced residents, particularly learners, to travel 26km to Louis Trichardt for library services.

In July 2023, Rembuwa Trading was awarded a R16-million tender.